September 1st 2011 :
All machines successfully installed and the testing and safety procedures review phase started.

September 24th 2011:
The plant is now ready in all aspects to start production. Estimated kick off date is the first of October 2011.

October 1st 2011:
Commissioning started, All seems well so far.

November 3rd 2011:
Processing and production is fully operational.